Punjab Development Program (PDP)

Jhelum City Infrastructure Upgrade

Improvement of Sewerage, Storm Drainage System, Street Pavements & Allied Infrastructure in North & South Areas of Jhelum City (District Jhelum).

Project Summary

Project Status

Work in Progress

Physical Progress

44%

North Zone Contractor
MAZCORP-ELITE-KUZU JV
South Zone Contractor
Al-Riaz Civil Engineering Services (Pvt) Ltd.
Design Consultant & Resident Supervision
M/s NESPAK (Pvt) Ltd.
Start Date
12-01-2026
End Date
15-05-2027
0
Project Schemes
0 km
Sewer Network
0
Tube Wells
0 km
Distribution Network

Project Overview & Scope

District Jhelum

15 km

Upgradation

76 km

New Sewerage

3 Nos.

Tube Wells

20 km

Distribution
Sewerage System

Upgradation of Existing: 15 km (North)

New Sewerage Network: 76 km (40 km N + 36 km S)

Total Sewer Network: 91 km (298,480 Rft)

Storm Drainage

Total Drainage: 28,480 Rft (8.7 km)

North: 4.7 km  |  South: 4.0 km

6'x6': 19,200 Rft

5'x4': 7,280 Rft

2'x2' & 2'x3': 2,000 Rft

Water Supply

New Tube Wells: 3 Nos. (North)

HDPE Distribution: 62,400 Rft (20 km)

Coverage: North Jhelum

Disposal & Pavements

New Disposal Station (Kotla Faqeer, South): 01 No. — 10 Cusec x1, 15 Cusec x2

Street Pavements: 190,786 Cft (0.8 M sq.ft)

Manhole Covers

Manhole Covers: 2,500 Nos.

HDPE Forcemain

HDPE Forcemain: 2 Nos.

Rehabilitation of Disposal Stations

Rehabilitation of Disposal Station (Sahil Colony, North): 01 No.

Up to Date Progress

Item-wise Status
North Zone
WorkLocationCompleted / Total (Rft)Status
RCC Sewer 36" diaNaya Muhallah to Muhammadi Chowk1,568 / 4,900 (32%) In-Progress
RCC Sewer 36" diaIqbal Library Road731 / 731 (100%) Completed
RCC Sewer 48" diaSalman Paras → Nirala Mart776 / 5,053 (15%) In-Progress
RCC Sewer 12" diaDhoke Muqarab1,376 / 6,071 (22%) In-Progress
Drain 4'x4'15 Bridge to Laari Ada370 / 4,600 (8%) In-Progress
Critical Components — Completed
RCC Sewer 48" diaSahil Colony to Shadab Pulley2,300 / 2,300 (100%) Completed
RCC Sewer 42" diaRiver Road to Chandni Chowk2,023 / 2,023 (100%) Completed
Drain 6'x6'Salman Paras to 15 Bridge2,340 / 2,340 (100%) Completed
South Zone
WorkLocationCompleted / Total (Rft)Status
RCC Sewer 54" diaKotla Faqir DS to Jaffer Road3,656 / 7,580 (48%) In-Progress
RCC Sewer 48" diaJaffer Road to New Christian Colony4,080 / 4,200 (97%) In-Progress
RCC Sewer 42" diaNew Christian Colony to Ibadat Chowk3,800 / 3,932 (96%) In-Progress
RCC Sewer 36" diaIbadat Chowk to Dera Ghosia3,752 / 7,610 (49%) In-Progress
Drain 6'x6'West Colony to MirzaAbad1,600 / 7,500 (21%) In-Progress
Disposal StationKotla Faqir70% / 100% In-Progress
Critical Components — Completed
RCC Sewer 27" diaJhelum-PD Khan Road to Bagga Village1,557 / 1,557 (100%) Completed
RCC Sewer 24" diaBagga Village to Saeela Village3,700 / 3,700 (100%) Completed
Drain 6'x6'River to West Colony5,900 / 5,900 (100%) Completed

Zone-wise Scheme Details

02 Schemes
PDP — North Zone, Jhelum
Status: Work in Progress

Improvement of Sewerage, Storm Drainage, Street Pavements & Allied Infrastructure in North Area of Jhelum City.

Contractor: MAZCORP-ELITE-KUZU JV  |  Consultant: M/s NESPAK (Pvt) Ltd.

Overall Progress
Physical Progress 36%
Up-to-Date Progress Remarks
  • Laying of RCC Sewer 4.32 / 55 Km completed & in progress.
  • Construction of RCC Drain 1.2 / 4.7 Km completed & in progress.
  • Design of Tube Wells by NESPAK is in progress.
CFY Target: 80% Physical Progress will be achieved during the Current Financial Year.
Key Works & Quantities
WorkQuantity
Rehabilitation of Disposal Station (Sahil Colony)01 No.
Sewerage System (New 40 km + Upgradation 15 km)Total 55 Km
Drainage System15,080 Rft / 4.7 Km
Water Supply Network (3 Tubewells, HDPE distribution)62,400 Rft / 20 Km
Street Pavements98,430 Cft
Machinery and Equipment25 Nos
PDP — South Zone, Jhelum
Status: Work in Progress

Improvement of Sewerage, Storm Drainage, Street Pavements & Allied Infrastructure in South Area of Jhelum City.

Contractor: Al-Riaz Civil Engineering Services (Pvt) Ltd.  |  Consultant: M/s NESPAK (Pvt) Ltd.

Overall Progress
Physical Progress 56%
Up-to-Date Progress Remarks
  • Laying of RCC Sewer 4.5 / 36 Km completed & in progress.
  • Construction of RCC Drain 2.5 / 4 Km completed & in progress.
  • Construction of Disposal Station Kotla Faqeer 70% completed & in progress (well sinking completed, plug PCC 1:2:4 in progress).
CFY Target: 100% Physical Progress will be achieved during the Current Financial Year.
Key Works & Quantities
WorkQuantity
New Disposal Station Kotla Faqeer (Pumps @ 15 Cusec x2, @ 10 Cusec x1)01 No.
Sewerage System (New)36 Km
Drainage System13,400 Rft / 4.0 Km
Street Pavements92,356 Cft

Pictorial Evidence

On-Site Progress
Restoration at 24Restoration at 24
South Zone
Restoration at 24" Sewer

Kotla Faqeer Village

Laying of RCC Sewer 54 Laying of RCC Sewer 54
South Zone
Laying of RCC Sewer 54" dia

Kotla Faqir DS to Jaffer Road — In-Progress (3,656 / 7,580 Rft, 48%)

Laying of RCC Sewer 48Laying of RCC Sewer 48
South Zone
Laying of RCC Sewer 48" dia at Jaffar Road, CMH

In-Progress (4,080 / 4,200 Rft — 97%)

Laying of RCC Sewer 42Laying of RCC Sewer 42
South Zone
Laying of RCC Sewer 42" dia at Christian Colony

In-Progress (3,800 / 3,932 Rft — 96%)

Laying of RCC Sewer 36Laying of RCC Sewer 36
North Zone
Laying of RCC Sewer 36" dia at Naya Muhallah

In-Progress (1,568 / 4,900 Rft — 32%)

(6' x 6') RCC Storm Water Drain(6' x 6') RCC Storm Water Drain
South Zone
(6' x 6') RCC Storm Water Drain at Cantt

Construction in progress

Sinking of Wet WellSinking of Wet Well
South Zone
Sinking of Wet Well, Kotla Faqeer Disposal Station

In-Progress (70%) — well sinking completed, plug PCC 1:2:4 in progress

(6' x 6') RCC Storm Water Drain(6' x 6') RCC Storm Water Drain
North Zone
(6' x 6') RCC Storm Water Drain at Bagh Muhallah

Completed (187 / 187 Rft)

RCC Pipe Factory — North ZoneRCC Pipe Factory — North ZoneRCC Pipe Factory — North ZoneRCC Pipe Factory — North Zone
North Zone
RCC Pipe Factory — North Zone

Manufacturing on-site (2,593 pipes up to date)

RCC Pipe Factory — South ZoneRCC Pipe Factory — South ZoneRCC Pipe Factory — South ZoneRCC Pipe Factory — South Zone
South Zone
RCC Pipe Factory — South Zone

Manufacturing on-site (3,349 pipes up to date)

Project Maps

GIS — WASA Jhelum
Proposed Sewerage System in Jhelum
Proposed Sewerage System in Jhelum

Proposed & completed work, PDP-1 WASA Jhelum

Critical Portion (PDP) WASA Jhelum
Critical Portion (PDP) WASA Jhelum

Critical locations of the project

Ongoing PDP Works — North Zone
Ongoing PDP Works — North Zone

Up to date progress

Ongoing PDP Works — South Zone
Ongoing PDP Works — South Zone

Up to date progress

Machinery Procurement Details

13 PDP  |  18 Available with WASA  |  31 Total
Sr. Machinery Name Procured under PDP Already Available with WASA Total
1 Suction Machine 02 01 03
2 Jetting Machine 02 01 03
3 Dewatering Set Nil 11 11
4 Manhole Desilting Machine Nil 02 02
5 Dump Truck 02 01 03
6 Excavator 02 Nil 02
7 Tractor Trolley 02 01 03
8 Roller Machine 01 Nil 01
9 Concrete Cutter 01 Nil 01
10 Plate Compactor 01 Nil 01
11 Water Tanker Nil 01 01
Grand Total: 0 0 0

Outcomes of the Project

22 Target Areas

Sanitation conditions will be significantly improved after the completion of the project across the following localities where new sewerage is being laid:

North Zone Areas
GT Road (Nawab Colony) Talian Wala Road (Chak Kasas, Chontra, Kharala) Kala Deo Madina Town Tehsil Road Dhoke Jumma Jadda Civil Line Road Kala Gujran Islam Pura Road Shumali Muhallah
South Zone Areas
Rohtas Road Makhdoom Abad Chittan Kotla Faqir West Colony Mirza Sharif Town New Christian Colony Arsal Town Kantrila Jinnah Colony Saeela